Concrete grades such as M20 look like codes, but each one stands for a simple recipe of cement, sand and coarse aggregate. This guide shows what the grades mean, how many bags of cement a cubic metre needs, and how to estimate a real slab.
The letter M stands for mix and the number is the target compressive strength in megapascals after 28 days of curing. M20 concrete is designed to reach 20 MPa. For small and medium jobs, builders use nominal mixes: fixed volume ratios of cement : sand : aggregate that are known to achieve roughly that strength without laboratory design. Larger structural work uses a design mix prepared and tested for the project.
The table uses a dry-volume factor of 1.54 and 1,440 kg per cubic metre of cement (about 28.8 bags of 50 kg per cubic metre of loose cement).
| Grade | Ratio | Cement bags | Sand (m³) | Aggregate (m³) | Typical use |
|---|---|---|---|---|---|
| M10 | 1:3:6 | 4.4 | 0.46 | 0.92 | Blinding, levelling, mass fill |
| M15 | 1:2:4 | 6.3 | 0.44 | 0.88 | Footings, plain concrete, floors on grade |
| M20 | 1:1.5:3 | 8.1 | 0.42 | 0.84 | Slabs, beams, columns in houses |
| M25 | 1:1:2 | 11.1 | 0.39 | 0.77 | Heavier loads, water-retaining work |
Always follow the grade your structural drawings call for. Foundations, columns and beams of habitable buildings are usually M20 or higher.
One cubic metre of finished concrete needs about 1.54 cubic metres of dry ingredients, because the loose materials contain voids that close up when mixed. For M20 (1:1.5:3) the total number of parts is 5.5, so cement is 1.54 × (1 ÷ 5.5) = 0.28 m³. At 1,440 kg per m³ that is 403 kg, or 8.06 bags. Sand is 0.28 × 1.5 = 0.42 m³ and aggregate is 0.28 × 3 = 0.84 m³.
Remember the steel: the Steel Weight Calculator converts bar diameter and length into kilograms, and the rebar weight guide explains the formula.
The Concrete Calculator handles slabs, footings and columns, applies the dry-volume factor and returns cement bags, sand and aggregate. Use the Volume Calculator first if your shape is not a simple box.
How many bags of cement are needed for 1 cubic metre of M20 concrete?
About 8 bags of 50 kg for a nominal 1:1.5:3 mix, together with roughly 0.42 m³ of sand and 0.84 m³ of aggregate.
Is a nominal mix as good as a design mix?
Nominal mixes are conservative and fine for ordinary houses. Large or heavily loaded structures need a design mix with tested materials, as specified by the engineer.
How long before I can remove formwork?
Typically 7 days for slab sides and 14–21 days for slab soffits, depending on span, weather and the engineer’s instructions.