← All guides · Updated 14 October 2026

Cement to Sand Ratio: Which Mix for Brickwork, Plaster and Floors?

A mix ratio such as 1:4 looks simple, but turning it into bags of cement and cubic feet of sand trips up many builders. This guide shows what the common ratios are used for, how a ratio becomes a shopping list, and the small factors that keep your estimate honest.

What a ratio means

A ratio like 1:4 is cement : sand by volume. One part cement to four parts sand means five parts in total, so cement is 1/5 (20%) of the dry mix and sand is 4/5 (80%). The same logic applies to 1:5 (cement is 1/6) and 1:6 (cement is 1/7). The weaker the mix (the bigger the second number), the less cement per cubic metre and the lower the strength.

Typical mixes and where they are used

RatioTypical useWhy
1:3Waterproof plaster, damp-proof layers, pointingRicher, denser and less permeable
1:4External plaster, load-bearing brickwork, floor screedGood strength and weather resistance
1:5Internal plaster, general brickworkBalance of cost and strength
1:6Non-load-bearing partition walls, internal masonryEconomical where strength is not critical

Local codes and engineers' specifications always come first. The table reflects common practice, not a substitute for your project's drawings.

From ratio to bags of cement and cubic feet of sand

  1. Work out the wet volume of the mortar or plaster (area × thickness, or the mortar share of a wall).
  2. Multiply by the dry-volume factor. Dry cement and sand pack with air between the grains and compact once water is added, so about 1.27 times as much dry material is needed (some sources use up to 1.33).
  3. Divide the dry volume by the sum of the ratio parts. Cement = dry volume × (1 ÷ total parts); sand = dry volume × (sand parts ÷ total parts).
  4. Convert cement to bags. A 50 kg bag is about 0.0347 cubic metres (1.226 cubic feet) at a density of 1,440 kg per cubic metre.

Example: 0.1115 cubic metres of wet plaster (100 sq ft at 12 mm) becomes 0.1416 m³ dry. At 1:4 that is 0.0283 m³ of cement, about 0.82 of a bag, and 0.1133 m³ of sand, about 4 cubic feet.

Sand quality changes the result

Sand with too much silt or clay weakens mortar however carefully you measure. Good building sand is clean, sharp and well graded. Damp sand also "bulks": it takes up more volume than dry sand for the same weight, so a bucket measure of wet sand gives you less real sand than you think. Measure with the same container every time, and keep the sand covered so its moisture stays consistent.

Mixing and curing tips

Related calculators

Use the Brick Calculator for mortar in walls, the Plaster Calculator for wall and ceiling finishes, and the Concrete Calculator when you need aggregate as well. They apply the dry-volume factor and bag conversion automatically.

Frequently asked questions

How many bags of cement are in 1 cubic metre of 1:4 mortar?

Dry volume is about 1.27 m³; cement is one fifth of that, 0.254 m³, which is about 7.3 bags of 50 kg.

Is 1:6 strong enough for brickwork?

It is widely used for non-load-bearing walls and internal work. Load-bearing walls and external work normally call for richer mixes such as 1:4 or 1:5, as specified by the engineer.

Why is the dry-volume factor needed?

Because cement and sand contain air when dry. Once they are mixed with water the voids fill, so you must start with more dry material than the finished mortar volume.

Related tools and guides

These guides give general estimating methods. Always follow your engineer's drawings, local codes and the instructions of the material supplier.